Site Plan Review
The Woburn Zoning Ordinance (the "Ordinance")
requires Trade Center Park to undergo a process known as "Site
Plan Review." During this review, City officials and
some neighborhood residents have cited off-site traffic issues
as their primary concern relative to the proposed completion
of Trade Center Park. This concern has prompted some people
to inquire as to what extent the Woburn Planning Board can
require an applicant to make off-site traffic improvements
as part of Site Plan Review.
|
|
A "by-right project." |
|
To answer this question, some background is
necessary. The Ordinance distinguishes between projects requiring
Site Plan Review for uses permitted by right, versus projects
requiring both site plan review and a Special Permit. This
is a critical distinction.
Trade Center Park is a "by-right"
project. A by-right development project is one that fully
conforms to all applicable requirements of the Ordinance,
including both the development's proposed uses and its dimensions.
The proposed new office space and parking garage do fully
comply with all relevant local zoning requirements including,
but not limited to, the square footage of new space, lot setbacks,
building height, floor area ratio, and percentage of landscaped
open space that will be maintained at the site.
A use allowed by right cannot be subject to
overly broad or subjective discretion, because that would
directly contradict the concept of "by right." Where
the proposed use is one permitted by right, the Planning Board
may only apply reasonable terms and conditions on the proposed
use, but it does not have discretionary power to deny whatever
use or uses of the property are authorized as of right in
the Ordinance for the applicable zone.
|
|
Review of traffic impacts. |
|
Turning to the question of traffic, Massachusetts
case law allows for strong argument that Site Plan Review
of traffic must be confined to on-site considerations (i.e.
that of access into and out of the site itself) and may not
include the roadways and intersections beyond the site.
In contrast to that position, the Ordinance
specifies that the Planning Board shall consider and render
its approval upon finding, among other things, the
"[a]dequacy of the capacity of local
streets to accommodate the traffic to be generated by the
proposed use. In making this finding, the Planning Board
may consider projections of increased traffic volumes due
to the proposed development, and the impact of such increases
on the levels of service on existing streets."
Whether or not this approach is correct, the
Ordinance goes on to make it clear that the Planning Board
shall consider off-site traffic only insofar as roadways are
"materially" impacted by the proposed use. Even
under the Ordinance, the Planning Board may not require a
by-right project undergoing Site Plan Review to mitigate traffic
problems that are independent of, or not materially worsened
by, its proposed use. Surely the Route 38/Elm Street intersection
will be materially impacted, as will the Beacon Street/Winn
Street intersection in Burlington, and both of these will
be corrected.
|
|
Off-site improvements will
exceed $1.9 million. |
|
 |
|
Click to enlarge
|
|
Notwithstanding any distinction between on-site
and off-site highway improvements, Cummings Properties has already
spent more than $700,000 on traffic studies and in rebuilding
Sylvan Road itself. It will also spend $1.2 million more, primarily
on the Route 38 / Elm Street / Sylvan Road / Alfred Street intersection;
the Route 38 Rotary, the Winn Street intersection and School
Street and Main to correct very longstanding deficiencies there
and elsewhere. This full project is expected to go out for local
and regional bidding as soon as the Planning Board votes to
accept the professional engineers' recommendations. The entire
Route 38/Elm Street project will be complete before this time
in 2007, if the work is approved now and authorized to proceed. |
|
|
|
|
|